Roadworks

Highways England accelerates switch to lower carbon asphalts

Highways England is accelerating the use of warm mix asphalts as standard across its supply chain as part of a drive towards net zero carbon emissions.

The government-owned company has been using the material since 2015 and a collaborative programme with the supply chain and extensive research now means it can be used freely across the strategic road network (SRN).

Previously requiring an application for a departure from standard, Highways England is now asking all those involved in the construction and/or maintenance of the SRN, particularly designers and main contractors, to use warm mix asphalts (WMAs) as it moves towards net zero.

WMA technologies can offer enhanced efficiencies and lower production carbon, with CO2 savings of up to 15% when compared to conventional hot mix asphalts.

While typical asphalts are produced at up to 190°C, the simple principle behind WMA technologies is to manufacture asphalt at reduced temperatures, but with additional additives.

Thereby, this uses less energy and delivers meaningful carbon savings, without compromising performance.

Produced at temperatures up to 40°C lower than traditional asphalt, if all production in the UK switched to WMAs, it would save around 61,000 tonnes of CO2 a year, the equivalent of cutting around 300 million miles of car journeys.

It would also help save up to £70m a year through an increase in shift outputs and can be recycled back into new asphalts, preventing waste.

WMAs can be laid using existing equipment and brings other benefits, including:

Carbon reduction
The lower production temperatures of WMAs reduce the carbon emissions associated with asphalt production by up to 15% compared to hot mix asphalts. More widespread use of WMAs will help Highways England to achieve its aim of net zero by 2050.

Increased productivity
Reduced laying temperatures mean that WMAs take a shorter time to cool, so greater volumes of asphalt can be laid in one shift, or the finished surface opened earlier to traffic without the risk of the material deforming under heavy loads. This will increase productivity by enabling more material to be laid within a working window, reducing the overall timeframe of the works and potential delays to motorists.

Improved health and safety
Reduced temperatures also help to reduce the health and safety risks associated with both production and laying of asphalt at high temperatures, such as burns, exposure to fumes and the impact of steam on visibility, particularly when wearing safety eyewear. With WMAs, fume generation is reduced by around 50% for each 10°C reduction in temperature.

Improved durability
Due to being laid at lower temperatures and the increased amount that can be laid in a single shift, it also means less construction joints in the road requiring less maintenance in the future. This again increases the long-term benefits of the technology, lifetime cost and need to undertake further maintenance.


Commenting, Executive Director of Commercial and Procurement at Highways England, Malcolm Dare said:

“This is a big step forward for Highways England that allows us to not only achieve huge efficiency savings, but also reduce carbon as we strive for net zero.

“Carbon reduction, along with ensuring our roads provide smooth, safe and efficient journeys for motorists, are key and something we are constantly striving to improve for generations to come.

“That’s why we are altering our way of working to encourage and enable the use of warm mix asphalts as standard across the supply chain, which has efficiency, sustainability and health and safety benefits, whilst not compromising performance.”

Carbon reduction lies at the heart of Highways England’s net zero carbon plan and the Department for Transport’s decarbonisation plan, with both aiming to shift the UK to a low carbon economy.

According to an All-Party Parliamentary Group on Highways’ report in September 2019, WMAs account for significant volumes worldwide, almost 40% of asphalt production in the USA and over 15% in France.

However, WMAs remain underused in the UK, where they currently represent less than 4% of overall asphalt production.

At Highways England, WMAs previously required an application from the supply chain for a departure from standard.

Having already received more than 250 applications to use WMAs on the strategic road network at over 300 locations, including, the M1, M4, M5, M6, A36 and A303, the change in policy will now make that process easier for the supply chain.

Highways England’s net zero carbon plan will see it rapidly cut carbon from road construction, maintenance and operations, and support the transition to zero emission vehicles. 

It has already stated sustained action towards decarbonising England’s motorways and A-roads so they can continue to bring significant benefits to motorists, communities and businesses in a net zero future. 

The plan will put roads at the heart of Britain’s net zero future through three key commitments:

  • Achieving net zero for its own operations by 2030
  • Delivering net zero road maintenance and construction by 2040
  • Supporting net zero carbon travel on the roads by 2050

PSE will be hosting a Public Sector Decarbonisation event on 9 September. Join us for the full day event by registering here.

PSE

PSE April/ May 2024

Alarming decline in UK costal water quality

Dive into our latest edition for April/May 2024!

 

More articles...

View all
Online Conference

Presenting

2024 Online Conferences

In partnership with our community of public sector leaders responsible for procurement and strategy across local authorities and the wider public sector, we’ve devised a collaborative calendar of conferences and events for leaders of industry to listen, learn and collaborate through engaging and immersive conversation.

All our conferences are CPD accredited, which means you can gain points to advance your career by attending our online conferences. Also, the contents are available on demand so you can re-watch at your convenience.

Public Sector Executive Podcast

Ep. 53 Compassion and Co-operation - Dr Nik Johnson

For the 53rd episode of the Public Sector Executive Podcast, Mayor of Cambridgeshire and Peterborough, Dr Nik Johnson, spoke to host Dan Benn about some of the most important issues facing his region, as well as what drives him as a leader.